The Botswana Power Corporation (BPC) will soon start construction of the long-awaited multi-million pula transmission line through which power from the 600-megawatt Morupule B Power Station will be brought to Greater Gaborone.

The 400-kilovolt line from the Morupule B Power Station to the Isang sub-station is one of key works in the 600-megawatt station’s development. The transmission line is essential for securing Gaborone’s future power supplies as its capacity creates room for the capital city’s growth.

The project, estimated at between P150 million and P300 million, involves the installation of towers, transmission lines, conductors and other machinery along the [continue reading]

About these ads



    Leave a Reply

    Fill in your details below or click an icon to log in:

    WordPress.com Logo

    You are commenting using your WordPress.com account. Log Out / Change )

    Twitter picture

    You are commenting using your Twitter account. Log Out / Change )

    Facebook photo

    You are commenting using your Facebook account. Log Out / Change )

    Connecting to %s



Follow

Get every new post delivered to your Inbox.

Join 36 other followers

%d bloggers like this: